Post-DANA reconstruction special plan

l’Horta Sud · Spain · 2025–2026

Technical data

Type of work
Post-disaster urban planning: special plan
Scale
Municipal: riverside and plots within the town
Studio’s role
Drafting of the full proposal: zoning, planning regulations and environmental, economic and gender documentation
River-affected zone
About 51 ha, of which about 49 ha is protected land with no building
Public parkland
3 floodable parks, about 2.2 ha · net gain of close to 0.9 ha
Period
2025–2026
Status
Proposal submitted

Description

After the DANA floods of October 2024, the municipality needed its planning to respond to flood risk with preventive measures. The general plan in force dates from the late 1990s and did not consider the effects of climate change on the frequency and intensity of floods, and the planning protection of the watercourse was limited to a narrow strip around the bed. Next to the channel, ordinary rural land held scattered uses —abandoned market gardens, sheds, storage yards and the odd workshop— and there was no open space at a territorial scale. In parts of the riverside, moreover, the ground falls away from the channel towards the town, so overflowing water tends to move away from the bed and is hard to drain.

The studio approached the response through planning, not just through works. Three alternatives were compared —doing nothing, carrying out mitigation works without changing the zoning, and combining them with a new land-use plan— and the third was chosen: without control of the land, the mitigation measures cannot be carried out.

The proposal designates a river-affected zone of some 51 ha that ceases to be ordinary rural land. Most of it, about 49 ha, becomes protected land with no building: new housing, vulnerable buildings and installations, landfill, storage, fencing and any obstacle that reduces discharge capacity are prohibited, while open spaces, walking and cycling routes and environmental restoration are permitted.

In the strip that adjoins the town, three public parks totalling about 2.2 ha are zoned with floodable design criteria: permeable paving, robust or removable furniture, no element that acts as a barrier to the flow, and solutions that allow the space to be brought back into use soon after a flood. The protective measure thus has an everyday use, because a space that is not used is neglected and ends up losing its function. The proposal also regularises as community facilities some plots zoned as parkland that in practice already function as facilities, and even so the balance of public parkland remains positive, with close to 0.9 ha more.

The studio drafted the full documentation for the proposal —information and justification report, information and zoning plans, planning regulations, strategic environmental documentation, economic feasibility study and gender impact report— and submitted it in successive versions between 2025 and 2026, in response to the municipal technical reports.

Gallery

Interpretive diagram prepared by the studio from the zoning proposal, not to scale.

Nine projects in l’Horta Sud.

Described by type, scale and stage.

  1. Reconstruction and resilience agendal’Horta Sud · 29 actions · Completed · 2025–2026
  2. Catchment study and DANA diagnosisl’Horta Sud · 5 sub-catchments · 2.7 km of channel · ~38,300 m³ eroded and ~47,700 m³ deposited · Diagnosis completed · 2026
  3. River channel clearance and reshapingl’Horta Sud · 2.7 km of channel · ~78,000 m³ removed · 1,750 m of bank with rock armour · Studies and outline design completed, permits in progress · 2026
  4. Channel renaturalisation and bioengineeringl’Horta Sud · ~570 m of rock armour ready for planting · 500 m of earth bank · 6 separable parts · Outline design in progress · environmental application submitted · 2026–2028
  5. Linear river park with flood-protection embankmentl’Horta Sud · ~1 km of riverside edge · Preliminary studies and concept · 2026
  6. Post-DANA reconstruction special planl’Horta Sud · ~51 ha of river-affected zone · 2.2 ha of floodable parks · Proposal submitted · 2025–2026
  7. Planning amendments for resiliencel’Horta Sud · 5 regulatory changes · 60 % of rainfall absorbed by SuDS · Detailed amendment approved · 2026
  8. Elevated crossing over a ravinel’Horta Sud · Deck of ~50 × 10 m · two lanes and a cycle and pedestrian path · Design in progress · 2026
  9. Urban regeneration and sustainable drainagel’Horta Sud · 6 projects · ~250 m² of draining tree pits and planters · ~500 m² of permeable playground · Detailed designs and costed reports · 2025–2026